On Thu, 9 Aug 2007, John W. Bienko wrote:
> Hawaii public works may wish to consider using the
> Heavy Lift Transporter to replace the driving surface
> of bridges requiring replacement. Here in Ottawa this
> weekend the construction crews have reserved 15 hours
> to do the work. All preparatory work.. the cutting of
> the existing damaged sections of the bridge are done
> without any significant interference to traffic flow.
> The new section is prebuilt beside the bridge. The 15
> hours is allocated to use the Heavy Lift Transporter
> to take away the old section and then to install the
> new section. The cost of the Heavy Lift Transporter
> is $2 million.
John... you don't mean it relaces the truss section
because of the term "road section"? Probably we don't
need it in Hawaii because most bridges here are made of
concrete. |