new arrangements at Bondi Junction commissioned?
"Tezza" <Tezza007@tpg.com.au> wrote in message
news:4463013e@dnews.tpgi.com.au...
> The railways own laws might have something to do with it as Craig has
> already pointed out
And I said, those issues aside...
>
>
> "Tony Gatt" <tony@railmedia.com.au> wrote in message
> news:4462f311$0$25132$afc38c87@news.optusnet.com.a u...
> >
> > "C. Dewick" <craigd@lios.apana.org.au> wrote in message
> > news:e3tltj$8rj$1@yoda.apana.org.au...
> >> Hi everyone,
> >>
> >> the weekend shutdown on the Illawarra had as one aspect of it the final
> >> commissioning of all the new track and signal arrangements at Bondi
> > Junction
> >> which were meant to have been put to use from Monday this week, leaving
> >> RailCorp still in breach of it's own Train Working Procedures out of
the
> >> Train Operations Manual (TWP-108, 110, etc. were the relevant ones).
Does
> >> anyone know if that's actually happened?
> >
> > Craig,
> >
> > Union/Management formalities aside, what makes the new arrangement so
> > difficult for drivers to be 'quickly' breifed on?
> >
> > On teh down there is a facing crossover so the protecting signal has
> > altered
> > aspects..
> > On the up there really is no change other than driving thru facing
points
> > out of #1 platform.
> >
> > So why the need for hours of wasted time and arrangements for the
> > commisioning of "1" set of facing points?
> >
> >
>
> |